The following appeared in the Rock County Herald on October 21, 1927:
ROAD GRADING CREWS MAKE STEADY PROGRESS ON T. H. NO. 9
Spectators With Leisure Time Get Constant Thrill from Machine-Like Operations of Contractors.
Rapid progress has been made during the past week by the double crews engaged in grading the new route for trunk highway No. 9, west of this city, but still the progress has not been as pronounced as many expected and the indications are that the job will not be fully completed before the end of next week.
P.J. Tobin, of Madison, S.D., the general contractor, who arrived last Monday with a complete two elevating grader crew, has since been working westward from the west end of Main street in this city, while Jarvis & Hale, of Hooker, Okla., the sub-contractors, who started on the west end in June, had by Wednesday night reached a point on the Birkholtz-Williams farm, three miles southwest of this city.
According to the “wise bystanders” the sub-contractors have been making the better showing the past week, but the general contractor’s crew has been under handicaps because of piece-meal stretches of grading at this end and the further fact that the new highway route leads through the Hinkly brick plant ruins and a considerable amount of tearing up and rapping loose was necessary before the elevating graders could be put to work at the brick yard premises.
Once this brick clay was loosened up it made a very satisfactory highway filling and for a considerable stretch a fill of more than three feet of solid brick was made. After the west crew gets through the Berkholtz-Williams farm, they will encounter a deep fill on the Jas. Preston place and an immense amount of soil must be moved before the attractive grades seen on the finished portions are attained.
Contrary to general rumor the state highway department is said to be standing pat on the time limit for finishing the contract and the necessity of paying a heavy forfeiture for each day after that time that the grading remains unfinished. The final date for completing the contract was October 15 and from that time on an “ante” of $300 a day is said to be the stipulation. This penalty will be borne by the sub-contractors, although the general contractor will be held responsible for its payment.
M.M. Youngman, of Sleepy Eye, who had done considerable surfacing on state aid roads in this county, the fore part of this week started graveling the six-mile stretch involved in the rerouting of trunk highway No. 6, in the south part of this county. His crew started moving gravel at about 1:00 o’clock Monday morning and by Tuesday night had surfaced about a mile, which would indicate that with continued favorable weather he will complete this job within a seven-day working period.
C.W. McNamara, of Sioux Falls, is expected to complete the grading of the new route for trunk highway No. 6, near Trosky, and it is quite likely that if Mr. Youngman completes the south end job as soon as expected, he will be given the surfacing contract at the north end.
Bids for the graveling of the new route for trunk highway No. 9, from this city to the South Dakota state line, were considered by the state highway department Tuesday, and it was expected that the job would be let at that time. In that event the successful bidder can start work from this end almost any day. It is understood that the gravel for surfacing this end of the new route will be taken from the Luverne sand and gravel pit at the south end of West Park street.
The interest of those having leisure time has centered in the grading contractors’ activities and their machine-like system of operation, and each day a great many people have spent hours in watching the crews move the dirt. The general contractor’s crew felt it necessary to work Sunday forenoon and a great many derived thrills from watching a caterpillar tractor and a blade grader rip away the wall formation at the abandoned brick yard. World war veterans were half inclined to believe that they were back in France in the World War days when they watched the caterpillar crawl in and out of the depressions.
Highway Construction Engineer E.J. McCubrey is leading an especially strenuous life these days, with three grading, two bridge building and one graveling crew under his general supervision.