Wind tower project moving forward

By
Brenda Winter, Reporter

The 119 wind towers slated for construction north of Luverne this summer should be producing power by the end of this year.
Geronimo Wind Energy spokesman Patrick Smith, along with other project representatives, attended Tuesday’s County Board meeting to update local officials on the project.
By the end of this year, the turbines will produce 200 megawatts of power.
Smith said the company has begun developing plans to add more towers north and east of the current site, which would go on-line in 2013 or 2014.
The Phase 2 towers would add another 100 megawatts to the grid.
Smith told County Commissioners Tuesday that construction of foundations for the towers will begin as soon as crews can get in the field in the spring.
He said soil borings revealed bedrock at depths ranging from two to 70 feet. Engineers will determine if any towers can be secured to bedrock itself. “I don’t think anyone was too surprised, but I can tell you from some of the cores we pulled out — that the bedrock is very hard.”
Geronimo director of operations Steve Mikel said the footings for each tower require 200 yards of concrete. A temporary batch plant will mix the concrete near the construction site.
 “We should start stacking towers by June. With the crane on site you can put up a couple of turbines in a day,” Mikel said.
Most of the construction materials will be delivered off I-90 and up Highway 23 in western Rock County.
Smith said the towers will come from Wisconsin, blades will come from Grand Forks and California and power cells will come from Florida.
County Engineer Mark Sehr reported the road improvements made for the project have brought the roads from a 2-ton capacity to a 20-ton capacity.
“They set it up really well. I know there is some concern about the aggregate,” Sehr said about the rough, washboard-surface roads.
“Because we’ve had no rain since August it hasn’t gotten packed like it should. The roads just need some water on them.”
Thirty-six miles of road were improved with 4 inches of 100-percent crushed granite in order to accommodate heavy equipment.
The aggregate will remain when the wind farm is complete, and the roads will continue to be maintained as usual, with gravel added when it becomes necessary.
When completed, the wind towers will be owned and operated by Enel Green Power in North America, which bills itself as a leading owner and operator of renewable energy plants in North America. It is a subsidiary of Enel Energy headquartered in Rome, Italy.