Skip to main content

Wind farm going up soon near Hardwick

By
Brenda Winter, Reporter

Geronimo Wind Energy’s Main Street office in Luverne was abuzz with activity last week.
Owners of the land where wind turbines will be located were signing final contracts, learning the turbine locations and hearing construction site safety guidelines.
Geronimo Wind Energy President Blake Nixon said that activity will soon be evident in the rest of the community.
May 7 is the expected mobilization date for the Prairie Rose Wind Farm scheduled to be built across 25,000 acres in northwest Rock County.
The group will establish its “lay down yard” of trailers and offices one mile north and one mile west of Hardwick.
Nixon said the work will begin in the southwest corner of the project and will occur in waves.
“It’s going to start slowly. In June you’ll start to see more traffic and the cement trucks. Building wind towers is like an assembly line — each phase covers 10 to 12 weeks,” Nixon said.
“The apex of the activity will be when the turbines are delivered, then the big trucks with really big components will be coming into the area over a 12-week span.”
If all goes according to plan, the wind farm will be generating power and online by December.