Tuesday night Hills-Beaver Creek School Board members met to discuss poor soil in the parking lot and road areas of the new construction site.
Superintendent David Deragisch explained how it was affecting work at the site.
He said it is too soft and unstable to be packed into a base for the road and parking lot.
“If you pick up two pieces of dirt and mix them together, similar to kids PlayDoh, once you are finished you are able to peel the pieces apart – they do not stick.”
He admitted it was a problem but questioned why it was not discovered when soil tests were done before the project began.
He asked board members if they thought the winter snow pack and wet spring could be contributing to the problem.
To determine the extent of the issue Gil Haugan Construction manager for the project brought in Goetek Engineering and Testing Services Inc. This is the same company that tested the soil during the winter of 2009. They visited the Hills-Beaver Creek High School construction site on May 18 to test soils.
The areas tested are located south and west of the school building. This area will become the parking lot and extension of Summit Avenue to the parking lot.
Also on hand were representatives from Gil Haugan and Reker construction companies and the H-BC School Board.
Goetek Engineering technicians took shallow hand auger borings ranging between 12 to 24 inches in various locations. They also took five samples of subgrade soils that contained lean clay soil.
A report from their laboratories indicate that the “in-site water content of the subgrade soils varied from 22 to 30 percent, which is 5 to 13 percent above the optimum water content.”
The report also states that the optimum water content of the subgrade soils should be 17 percent.
Based on their findings Goetech Engineering recommended to stabilize the subgrade soils at the project site. The rate of mixing would vary based on the severity of the soft/wet subgrade conditions.
The board then reviewed information supplied by Gil Haugan.
Option presented by
Gil Haugan Construction
Gil Haugan used the Geotek recommendation to put together a cost proposal for stabilization of the soil.
Instead of using fly ash — a material used to make cement — workers opted to use cement to stabilize the soil instead. Fly ash is not available locally and would have to be trucked in from Minneapolis; adding to the cost of the change order.
Midstates Reclamation, the contractor contacted to do the work, recommends using 5 to 7 percent cement in the top 12 inches of soil.
The actual amount of cement needed will not be determined until the work is complete. The cost range based on these percentages is $60,037.41 to $82,457.50.
Gil Haugan based its proposal on 7 percent. The cost to Midstates is estimated at $82,457. There would be a $20,500 credit back from the Reker Construction bid for the 12-inch subbase work. An additional $6,800 is needed for compaction and leveling and $7,500 for subbase work through Henning Construction. A Construction Manager fee of 3 percent ($2,287) goes to Gil Haugan. The total cost of the change order is $78,545.
The cost proposal stated that the process would not change the work schedule at the site.
Board opts to wait
for more options
Building Committee Chair Ann Boeve expressed concern with only having one option to choose from and that the option was expensive.
Deragisch agreed, adding, “I asked today if using Portland cement would give us a 100-percent guarantee of fixing the problem, and I was told no.”
Board member James Kueter responded, “They want us to spend $70,000 to $80,000 with no guarantee?”
Deragisch asked for suggestions that he could take to the construction manager during a meeting on Wednesday.
He said he spoke with Rock County Engineer Mark Sehr who has worked with fly ash before. Deragisch was going to invite him to the meeting to speak about working with the product. He also was going to ask for a quote to use the product.
Board member and building committee member Harley Fransman expressed his concern that the problem may be a result of wet conditions and suggested it might be a solution to use a gravel road and parking area during the first year.
“Maybe having gravel for a year is a viable option.”
Fransman continued, “We can check things in a year to see if they have improved.”
Boeve warned that not completing the road as stated in the contract might result in a delay in being able to use the building.
Deragisch said he would check into the situation before exploring the option of waiting.
Boeve said the board should not make a decision until it had more information and recommended getting a second opinion on the soil samples.
Board chair Gary Esselink asked Deragisch to continue to gather more information and stated, “We are not in any rush and want to do this right — we will not be pressured to make a quick decision.”
Other construction business
•Utility work has started along the center of what will become North Summit Avenue. Holes 16 to 18-feet are being dug to put in water and sewer lines, as well as installing manholes.
•Basketball hoops have been installed in the gym and the scoreboards are being picked up Friday.
•Electricians will start work Friday.
•Deragisch was given a completion date of Aug. 5 for the building.
•All high school students and staff toured the building on the final day of school.
Unstable soil causes concerns for
construction site road, parking lot