extension on federal grant funding for tunnel while other options are explored
It’s possible the much-debated pedestrian tunnel in Luverne may not happen this summer.
That’s according to discussion at a county-city-school liaison committee meeting Monday with an engineer from Minnesota Department of Transportation.
At Monday’s meeting, local officials heard convincing arguments for alternatives to the proposed $840,000 tunnel under Highway 75.
MnDOT traffic engineer Scott Thompson presented options to get students safely across Highway 75, and some of those sounded viable to the committee.
In particular, they’re researching the merits of a High-intensity Activated Crosswalk (HAWK) system at one of the school crossings.
Walkers push a button that triggers a red light for cars. With the right of way, pedestrians are given time to reach the other side of the street before the light goes back to being dark and cars can move again.
Two lights are requested because students won’t cross at one point
At the same time, committee members will begin to lobby for a second HAWK system, arguing that students will not likely use a centrally located light placed where a tunnel would have been installed.
Thompson said HAWK systems cost about $200,000 and qualify for some state cost sharing.
He said he was unsure that the volume of pedestrians crossing the highway would meet the state’s guidelines for installing a HAWK and he doubted the state would approve two lights being placed so close together.
Committee members suggested that local governments would be willing to pay for a second light if MnDOT would not, and to lobby at the state level to get the second light.
Thompson said approval for the HAWK system would require a letter to District 7 Engineer James Swanson and then approval by the state’s traffic safety engineer.
Thompson said the timeline for installation depends on the county’s and the state’s capacity for plan design.
Thompson said other kinds of flashing LED crossing light systems exist that would not require approval from “higher-ups” and can be installed for $15,000 to $20,000.
State has its own plans for Highway 75
Thompson explained how changes planned by the state for Highway 75 through Luverne in 2013 will benefit pedestrian safety.
Re-striping the highway from a four-lane to a three-lane has “a natural traffic-calming effect,” according to Thompson.
“Speed decreases as the perceived width of the roadway decreases. Three lanes cause drivers to slow down and it takes out that blind spot,” Thompson said.
“These are changes that will definitely benefit pedestrians.”
Rock County Sheriff Evan Verbrugge said the biggest problem with speeding into the school zone comes from the north and most citations are given to out-of-town drivers. He said that was the case with an elderly driver cited last week after driving through the crosswalk claiming he did not see the crossing guard or the flag.
One centrally located crossing point is safest
A committee member asked Thompson what he thinks is the safest way to get people across the highway.
Thompson said, from his point of view as a traffic engineer, having all students cross at one point is safer than three crossing points.
“There is safety in numbers. It’s easier to see a larger group crossing all at once,” Thompson said.
“Even three crossing guards that close together seems like overkill to me.”
He added that asking drivers to stop too many times can build frustration into the system and cause drivers to stop paying attention.
“We (at MnDOT) are interested in the safety of kids, too, but asking motorists to stop three times doesn’t seem right,” Thompson said.
“The 30-mph speed limit, 25 during school, is a really slow speed. We have every device we can have at the north end of town and nothing at the south end? The lack of (pedestrian) crashes shows the system is working.”
Committee to lobby state officials; county to seek extension of tunnel grant
County Engineer Mark Sehr was directed to request a meeting of the liaison committee, Rep. Joe Schomacker and Sen. Doug Magnus, District Engineer Jim Swanson and State Traffic Engineer Sue Groth to pursue the installation of one HAWK traffic light followed by a second.
Sehr said. “I’ll see what I can do.”
He said he will also request that federal grant money for the tunnel be extended from 2012 to 2014 without losing the funding as local officials continue to discuss options.