Skip to main content

Soil conditions
lead to pricy change order

By
Lexi Moore, Editor, Hills Crescent

Following a lengthy discussion on Monday night, Hills-Beaver Creek School Board members voted to approve a $160,000 change order.
The action allows the use of gravel fill to stabilize soils along the road (North Summit Avenue) leading to the building.
The recommendation to approve the change order came from the building committee and Superintendent David Deragisch. 
On Wednesday, June 8, this group met with representatives from Gil Haugan Construction, Koch Hazard Architects, Reker Construction, Geotech Engineering, Henning Construction and the city of Hills.
The group met for more than four hours to discuss the issue of unstable soil at the work site. The ground in the road area has been tested twice in the last month and is largely made up of loess soil.
Loess soil is too soft and unstable to be packed into a base for a road, especially in areas were the trench to place utilities is 18 to 20 feet deep.
A solution of using granular subbase and gravel was determined to be the best option. During their meeting a Henning Construction representative went to the site, taking three measurements to determine an estimate of how much gravel would be needed.
Based on these estimates and the price of gravel the group collectively decided a $160,000 estimate would be on the high side for the project.
Building committee member Harley Fransman said, “We went over this many times that day and it kept coming back to this being our only option.”
He went on to explain that although moisture is a problem, it is not the only problem.
“It is the combo of moisture and this type of soil,” Fransman said. “Things just won’t dry out.”
Gil Haugan stated at the meeting that if the district opts to use this solution it would guarantee the work. 
If the district opts to continue with the project according to the original specs, the work would not be guaranteed and the School Board would be required to sign off on that fact.
Board member Jim Kueter asked how long the guarantee is good for and if the contract caps the estimate at $160,000.
Deragisch said he did not know how long the guarantee lasts, but would find out. Committee Chair Ann Boeve said the contract does not include language about a cap, but the group estimated high.
Deragisch added, “I made sure they knew we were not interested in spending even a penny over this estimate.”
Kueter asked if the committee felt comfortable with this solution.
Boeve said, “I think it is a good solution —unfortunately it is an expensive solution.”
 
Funding the change order
Kueter asked how the district was sitting financially to pay for a change order for this amount. Board Chair Gary Esselink echoed his concerns and asked Deragisch to explain the current state of bond funds.
Deragisch handed out the original bid sheet, along with a running total for the project.
A $190,000 contingency fund was included in the original bond. Previous change orders have used a portion of this fund, bringing it down to approximately $140,000 available.
Deragisch explained there are some additional funds that can be used. Those come from an $18,722 credit and $71,000 in interest earned on the bond funds. He also pointed to $210,000 in the general conditions fund.
This fund pays for site expenses, including snow removal, heat and porta-potties. At this point only $73,000 has been used.
The final item he pointed to was a potential reimbursement from the City of Hills for utilities to the site and a portion of installing the road.
The district talked to the city on several occasions about making a contribution but a formal agreement has yet to be reached.
Boeve explained that from what she understood the Hills City Council plans to make a donation but the amount is not known. Last fall Deragisch presented the council with a breakdown of costs for utilities and a city’s portion of the road, the total was $205,000.
Without adding a city donation or deleting any money from the general conditions fund the change order would put the district over its $9.9 million bond price. The running total would be at approximately $1,039,410.
Boeve explained that the expense of putting in a road and utility work were included in the bid package but this change order doubles the bid price for this package.
“A reimbursement from the city is going to really help us out,” she said.
 
The plan for parking
Also in question was the stability of the soil in the parking lot areas of the school.
Initially the board had been informed this area would need to be stabilized. Another engineering firm visited the site and said because there is no utility trenching in the parking areas the ground can be stabilized using a small layer of material.
The board looked at two different options but did not have pricing for either.
Committee member Tim Baker said, “We are sticking with the original bid until someone can prove to us that is won’t work and show us figures on what will.”
 
DeWandel retires and is hired back part-time
Deragisch explained the cost benefits of accepting a resignation from Greg DeWandel as full-time ag instructor.
DeWandel qualifies to collect from the Teacher Retirement Association but does not want to be done teaching.
The school has the option to accept his resignation as a full-time educator and hire him back as a .8 FTE teacher at a lower wage.
DeWandel will continue to teach the same courses and advise the Future Farmers of America program. He will not have to arrive early or stay after school for prep periods.
Deragisch said this saves the district $15,000 in salary.
The board approved both the resignation and the re-hiring of DeWandel.
 
In other business:
•The board accepted the following donations for the summer Book of the Week program, $1,000 donation from Minnwest Bank and a $150 donation from Early Childhood Initiative/SWMN Foundation.
•The board recognizes the efforts and achievements of H-BC graduate Whitney Wilgenburg who finished in 12th place in the 3,200-meter run at the Minnesota State High School Track Meet in St. Paul June 10-11.

You must log in to continue reading. Log in or subscribe today.