By Brenda Winter
Rock County Commissioners agreed that roads, bridges and the funding of them remain a hot topic in the budget process, especially after the county moved the scheduled repair of two bridges on County Road 13 ahead two years in the five-year plan.
Commissioner Stan Williamson, whose district includes the two bridges on County Road 13 west of Hills, said he thinks replacing the load-limited bridges is a top priority and needs to happen now.
“Right now the attention has to go to Martin Township.”
County Administrator Kyle Oldre said he agrees Martin Township bridges are in need of replacing, but moving two bridges ahead on the five-year replacement plan means some other work gets moved back.
“Unless you plan on adding bridges in a year you’ve got someone else who says, ‘What about mine?’”
County Engineer Mark Sehr said his department completed work on half of the bridges scheduled for replacement this summer. He said roadwork boils down to time and money – and his department doesn’t have extra of either.
Replacing the two bridges west of Hills will cost an estimated $200,000. “We’ll have to peel back a quarter mile of blacktop,” Sehr said.
The bridges were posted for load limits following an inspection by the state of Minnesota earlier this summer.
Sehr said the county hopes to replace the bridges with box culverts before the 2014 harvest season begins.