New bridge replaces old 'hump back' bridge

By
Brenda Winter, Reporter

Since the new bridge appeared on County Road 55 between Luverne and Magnolia last week, Rock County Highway Engineer Mark Sehr has been answering one question, “Is it supposed to look that way?”
His answer, “Yes.”
The new bridge built over the rail line slopes downhill from its south end to its north end.
Because the distance is short between the end of the bridge and the stop sign for County Road 4, the slope begins on the bridge itself.
“Because we have to be so high over the railroad and get back down to the road level we took care of some of the slope on the bridge,” Sehr said.
In addition to the slope, Sehr said the bridge is employing technology never used in Minnesota before. 
The abutments are made of geosynthetic reinforced soil, and no pilings are being used.
Sehr said the hoped-for benefits of the construction are the facts that it is easier and cheaper to build.
The bridge, costing roughly $550,000, is paid for by Federal “Innovative Research Bridge Demonstration” funds and Minnesota bridge bonding funds.
It is scheduled to be open to traffic by the end of June.