More wind towers coming

By
Brenda Winter, Reporter

The developer of Prairie Rose Wind Farm in northwest Rock County is considering a 100-megawatt expansion in the next three years, according to Geronimo Wind Energy director of development, Justin Pickar.
Prairie Rose Wind Farm is a 119 tower, 200-megawatt wind farm that was completed near the border of Rock and Pipestone counties in 2012.
Pickar said Geronimo has begun contacting landowners in the proposed project area and informing them of the specifics of “Phase 2” for the Prairie Rose expansion.
Approximately 50 towers will be needed to generate 100 additional megawatts. Pickar said half of the new towers would probably be built in each county on land contiguous to the existing wind farm.
As wind tower technology advances, higher megawatt turbines are being built. Pickar said more efficient blades are resulting in increased production.
At the very earliest, additional towers could be built by 2015, but Pickar said 2016 to 2017 is a more likely time frame.
Prairie Rose Wind Farm generated about $610,000 in taxes for Rock County in 2013 and about $150,000 for the townships in which the towers are located.
Rock County Commissioners are considering putting that wind revenue toward road improvements countywide.