Water availability in northeast Rock County will become less susceptible to drought thanks to an estimated $3.6 million project proposed by Lincoln-Pipestone Rural Water System (LPRW).
Mark Johnson, LPRW chief executive officer, and LPRW commissioner Jerry Lonneman met with Rock County Commissioners June 2 and outlined seven priority projects within LPRW’s 10-county area including Rock County.
The project in Rock County is LPRW’s priority project, Johnson said, and application has been submitted to USDA Rural Development for funding.
The application includes the construction of a second connection point to the Lewis & Clark Regional Water System near Magnolia. Another priority will be to construct a pipeline from Magnolia north to Edgerton.
“This is going to be helpful to us to get water to the main heart of our system,” Johnson said.
LPRW serves the Magnolia, Kenneth, Hardwick and Jasper areas.
“It’s very critical and important to us to have drought protection,” Johnson said.
Also presented at the meeting was the 2014 LPRW annual report.
Johnson said the audit by Meulebroeck, Taubert & Co was a clean opinion and noted operating expenditures increased by $77,568 over 2013 and operating revenues increased by $321,637.
In 2014, LPRW had $4.5 million in operating revenue and $6.5 million in expenses. The expense increase was primarily due to paying $4.2 million in debt, refinancing $2.9 million.
In other business, the commissioners:
•Approved the city of Hardwick’s request to purchase the tax-forfeited property at 105 N. Ross St. for $1 plus fees. A portion of the lot will be given over to Alliance Communications of Garretson, S.D., to construct a fiber-optic hub.
•A .87 percent interest rate was received for the $2.4 million Rock County Rural Water project construction bond sale. The loan is for two years.
The sale was handled through Northland Securities of Minneapolis.
LPRW outlines priorities with Rock County Commissioners
By
Mavis Fodness