The washed-out bridge on 111th Street north of Beaver Creek is scheduled to be repaired by Dec. 15.
Rock County Engineer Mark Sehr told county commissioners the Highway Department is accepting quotes for the long-delayed project Nov. 7.
Sehr said the washout was noticed in March of 2013 but the repair process is complicated.
Commissioners acknowledged the frustration of local farmers who have been forced to reroute their tractors and wagons for the 2013 growing season.
Sehr said the hold-up with the project lies with the Army Corps of Engineers. “It’s not MnDOT. You can call your local representatives, but this isn’t their jurisdiction.”
Sehr said he began the permitting process in July and was pleased that it took only three months for the Corps to approve the plan.
“It appeared that we weren’t doing anything,” Sehr said, “But we were waiting.”
County Administrator Kyle Oldre said because the cost of the repair to the bridge was less than $100,000, the county could employ a quote process instead of a bid-letting process. “That saves a lot of time.”
Work on the bridge should begin immediately.