Rock County Land Records Director and Hills assessor Tom Houselog presented the Hills City Council with information regarding home values during the annual Board of Appeal and Equalization meeting on Tuesday, May 8.
Houselog informed the board that, based on nine sales from October 2010 to September 2011, overall there was not much change in the city values.
Residential values slipped approximately half a percent during that time.
There was only $66,000 in new construction during that time, compared to $1.2 million the year before.
Agricultural land in Hills increased 23 percent, as did all tillable land in Rock County.
Hills to proceed with public works projects
The council approved several projects to improve the roads and sewer in Hills.
Leuthold Plumbing, Heating and Electric submitted quotes for three projects.
Their quote included several options for bringing city water into the campground at the Rez.
The quote was for 1,600 feet of pipe and a hydrant installation.
One price at $5 per foot was for installing 2-inch yellowmine, including couplings and borings or installing 2-inch PVC at $3 per foot.
The footage was based on bringing water from the highway.
The city had contacted the Burlington Northern Railroad to find out about boring the water line under the railroad tracks on the east side of the park. The railroad requires filing an application along with a $600 application fee.
The council voted to ask Leuthold to proceed with completing the application and getting a quote to bore under the railroad.
Leuthold also submitted bids to replace the sewer line in the alley between Second and Third streets. They also approved sewer repairs along South Central and Anna Avenue.
The council approved repair to damaged waterline near Erwin’s Station. The work was completed last week.
A quote from Reker Construction was approved for work on half of Seventh Street and South Anna Avenue, as well as constructing Orchard Lane.
The cost of the three projects will be $19,500 and does not include asphalt surfacing.
The city plans to tear up the existing surfaces on Seventh Street and Anna Avenue and replace them with a base. Drivers will pack the base down before asphalt is laid.
Orchard Lane in the northwest corner of town will be constructed.
Public Works Superintendent Eric Harnack was asked to obtain a quote from SW Sealcoating to fill approximately 70 potholes.
Maguire Iron Inc. will install a new roof/shell on the water tower for $2,200.
In other city business:
•Doug Chapman approached the council regarding electricity at the site of the American Legion Memorial. The city will allow Chapman to install a meter socket on the street light pole.
The Legion will pay for the installation of the meter, lights and wiring and the city will pay for the monthly service and the installation of an additional outlet.
•approved the rental of a boom truck from Doug Kraayenhof for the purpose of trimming trees.
•Decided to proceed with contacting the city attorney to go to residents with junk car violations. Residents have already been notified by the city.
You must log in to continue reading. Log in or subscribe today.