Hills expands north

The Hills City Council passed an ordinance adding approximately 50 acres to the city on the northwest side of town.
The annexation of the property brings the new Hills-Beaver Creek high school building site, as well as the ground needed to extend Summit Avenue, into the city limits.
It also officially gives the new school building a Hills address, 300 N. Summit Ave.
 
Council to open sewer rehab bids in May
Tom Wall of DeWild, Grant, Reckert and Associates appeared before the Hills City Council to present the final specifications for two upcoming sewer rehab projects.
The first plan detailed adding a 428-foot, 10-inch sewer line to bypass the high school football field.
The bypass eliminates a sagging 8-inch line that runs through the field.
The council approved the specifications and asked Wall to submit them to the Minnesota Pollution Control Agency for approval.
Once the project is approved, the city can begin work.
The second plan laid out a bid schedule for the remaining sewer rehab work.
The bid calls for 3,080 feet of sewer pipe to be cleaned, televised and lined.
Lining the sewer lines with a hard resin creates seamless pipes. The targeted areas were determined based on high flows.
Additionally the bid asks for a price to grout and repair six city manholes and two gates at the city ponds.
Bids will be opened at noon on Monday, April 9, at City Hall.
Wall will review the bids and present a recommendation to the council at their meeting the following evening.