Rumors are swirling that Luverne’s highly anticipated Highway 75 construction will not be done this year.
According to City Administrator John Call, those rumors are both true and false.
The actual road surface construction is indeed on hold due to several factors delaying the project.
But there will be significant boulevard and infrastructure improvements completed this fall.
 
Waiting for Topeka shiner
A culvert replacement on Poplar Creek near the McClure property cannot start until after Aug. 15 in order to protect the mating season of the endangered minnow, the Topeka shiner.
That was known at the start of the planning project, but the state didn’t turn in its plans and specification for the culvert until two weeks ago, delaying the bid date and actual start time for the culvert work.
 
Soil testing shows 
pretroleum contamination
Also delaying the project was the need for soil testing in that area because the city is replacing an aging waterline on the west side of Highway 75 from the McClure property north to Main Street.
Because there was at one time a service station in that area, and because it’s in a state right of way, the state required soil testing before major dirt work could start.
Call said the state hired a firm to do the soil testing at the city’s expense — roughly $60,000. 
“The soil testing was extensive, and we’re trying to get the bill reduced, because we — our engineers — don’t think we needed that much testing,” Call said.
Soil test results, released last week, revealed petroleum-based contamination, so some of the soil in that area needs to be removed before work can begin.
“It’s not extremely bad,” Call said about the contamination, “but it has to be included in the plans and specifications for that part of the project, and it slows everything down.”
He said the city will apply for state grants to help pay for soil cleanup.
Ultimately, Call said the earliest the waterline and culvert project could begin would be September or October.
 
Road surface work 
delayed until next year
The mill off and overlay of South Highway 75 and the resurfacing of North Highway 75 will not happen until next year.
Actual road surfacing work can’t begin until the culvert and waterline replacements are done, and many contractors won’t bid on projects that start in the fall.
In order to leverage more competitive bids, Call said state and city engineers advised a spring start for the road surface work.
 
City ponies up funds 
for state roadwork
Since Highway 75 isn’t on the state’s five-year road plan, Luverne is subsidizing 25 percent of the cost of milling off and overlaying the Highway 75 surface south of Main Street.
The city’s portion of that expense is expected to be roughly $100,000.
The city had hoped to receive grant support for its share of the north portion, but Call said that grant didn’t come through.
As a result, the north portion, from Main Street to city limits by the hospital, may amount to only an overlay.
Call said the city is subsequently negotiating with the state on a 25-percent cost share for a mill off and overlay of the north portion of the state work.
“The whole thing needs a complete rebuild; it’s in bad shape,” Call said, admitting that it’s difficult to accept state road improvement priorities. 
“It’s quite a huge undertaking to understand the state’s budgets for roads.”
The good news, Call said, is that sidewalks, boulevards and light poles will be completed on schedule this fall. (See related story about aesthetic improvements)
“We’re hoping to see significant construction yet this fall,” he said.
 
What’s been done so far, what’s next on agenda:
2012 and 2013 have already been big construction years for South Highway 75.
Last year, boulevards were torn up for infrastructure work — major water and sewer line replacement from Mead Court to I-90 on the west side of the road.
This year (and into this fall), boulevards were repaired and replaced with added green space and new sidewalks. 
Luverne’s total Highway 75 investment for last year amounts to $800,000 that includes the below-ground infrastructure work and above-ground aesthetics.
Cost estimates for this year are being revised, with bid letting set for late August and work starting  in September or October.
Next year will consist primarily of road surface work, which will be mostly state expense, except for the 25 percent Luverne cost share.