Construction on Highway 23 from Pipestone to I-90 is well underway, with the surface milled off and a new concrete roadway being poured.
Traffic is detoured east on I-90, north on Highway 75 through Luverne and west on Rock County Road 12 to Pipestone County Road 1.
The Highway 23 project is split into two segments. The northern segment, from Pipestone to Jasper, removes and replaces the top three inches of pavement and is done under traffic using flaggers and a pilot car.
The southern segment, from Jasper to I-90, removes the existing pavement and replaces it with a drainable base and six inches of concrete.
The Highway 23 projects are scheduled for completion in July, weather permitting, and will provide a smoother and safer ride for motorists.
The project cost for the Pipestone segment is $4.4 million and the I-90 segment is $10 million.
Highway 75 project begins in August
Two culverts on Highway 75 south of Trosky will be replaced in the fall and will require a detour from August to November, weather permitting.
The detour follows west on Rock County Road 12 and Pipestone County Road 1, north on County Road 15, east on County Road 2.
The Highway 75 safety enhancements cost $1.05 million. They will improve drainage and provide a safer road surface for motorists.
Duininck Inc. is the contractor for all three projects.