Hills-Beaver Creek Building Committee members came to the School Board Monday for direction.
They asked for help making decisions on change orders for Summit Avenue and the high school parking lot.
In the parking area south of the school the original bid called for 21 inches of subbase material and five inches of asphalt sitting on top of a geotextile fabric.
The specifications also call for removing an additional foot of soil.
GeoTeck Engineering, the company responsible for checking soil conditions, recommends digging farther down and using additional fill.
It is estimated that this method will cost the district $108,000. Using this method will qualify the district for a one-year warranty on the work done.
If the district opts to use the original specs, that warranty will not be valid.
Building Committee member Harley Fransman said he and the committee were leaning toward using the specs bid out of the bid package.
He also reported that the engineer who drew up the specs still defends them.
The board agreed that the cost of adding fill to such a low traffic area was not in the best interest of the district.
Jim Kueter made a motion to build the parking lot area according to the original specs. It was seconded by Lois Leuthold and approved by the board.
The committee moved on to discuss issues that continue to stall progress on Summit Avenue.
Superintendent David Deragisch reported that the sewer and water utilities have been installed along the road and are safely buried.
He added that gravel fill has been placed but is still three feet short of grade along the utility trench in the middle of the road.
At their June meeting, board members approved a change order to purchase $160,000 of gravel to help stabilize soil along the road.
As of Monday night the district has spent $138,000 on gravel.
Deragisch laid out several options for finishing the road.
Option 1: Purchase more gravel to bring the road to grade. This includes cutting out the sides of the road and filling that area with gravel as well. It was reported to be the most expensive option and the one recommended by GeoTech.
Option 2: Use glacial till soil to fill the area. There is some of this soil currently on the property, but it is estimated to only be enough to complete one block of the project.
Option 3: Haul in outside dirt.
Option 4: Use the foot of dirt that will be removed from the parking lot area in addition to dirt already stock piled on site to fill the area.
Glacial till runs $7.75 per yard, if hauled in from off-site. Gravel costs between $8.75 and $10 per yard.
Deragisch explained that currently Reker Construction is working on the north portion of the parking lot, using on-site dirt.
It is taking more time to disk and work the dirt but it is passing both compression and moisture tests.
Henning Construction, who did the utility work is responsible for bring the utility trench to grade. They maintain that the soil is not suitable and that fill needs to be brought in.
Committee member Baker asked, “How do we handle it when one guy is making it work and the other is refusing?”
Fransman echoed Baker’s frustration saying that information changes daily and is often conflicting.
Board Chairman Gary Esselink and Kueter asked what role construction manager, Gil Haugan, has played in these decisions.
They requested that those representativesplay a larger role in such discussions, including being an advocate for the district, not contractors.
Esselink said, “This is when they need to step up.”
Kueter agreed, “We are spending a great deal of money with them and they should be fighting for what is in our best interest.”
Esselink also asked for the city of Hills to get involved in the situation because they will be caring for the road in the future.
He requested the building committee arrange to meet with the council, along with either the engineer or the Gil Haugan representative. The council met Tuesday night with Fransman, Baker and the construction manager.
They explained that the board intends to stick with the original specs and if the council wanted to take additional measures they would need to pay for it themselves.
Deragisch said waiting to make this decision will not slow down progress at the site, because things can still get done in the building and work is being done on the parking area.
Esselink informed the board members they might have to have a special meeting to facilitate the discussion.
Building update
The building committee reported the following items are being worked on or completed at the high school building site. The board plans to walk through the site during the July 25 meeting.
•This week and next contractors will be flushing and filling the geothermal heating and cooling system in preparation for turning it on.
Once the geothermal system is working humidity in the building can be controlled, this will allow for the gym floor to be delivered and to acclimate to the environment.
•The electrical outlets and lights are functional.
•Classrooms are being cleaned and built-ins installed.
•The elevator is complete and ready for use.
•Painting continues in the ag and industrial rooms, along with door frames.
State shutdown will not slow down project
Despite being the only state project in Rock County, the Minnesota government shutdown will not affect work at the job site.
State inspectors cannot inspect the property during the shutdown, but there are few things that still need to be inspected.
Deragisch reports that a final plumbing and overall building inspection will be required, but not until the project is finished.
Additional electrical inspections are also needed but electricians are continuing to work with the idea that things will be inspected at a later date.
“Our contractors have a good working relationship with the state inspectors and spoke with them the week before the shutdown,” Deragisch said. “We are not letting it hold us back.”