Last week the Hills Crescent office received United States District Court documents detailing a complaint filed against the Hills-Beaver Creek School District.
The complaint was filed June 19 on behalf of the plaintiff, Gil Haugan Construction.
It states that the district is liable for an amount exceeding $483,742, plus interest, attorneys’ fees, costs and sanctions under Minnesota law.
H-BC Superintendent Todd Holthaus said the School Board is aware of the complaint.
The board began the legal process at that time and is currently not speaking on the matter under the advice of legal counsel.
The next step is for them to file an official answer to the complaint, which would include the amount they believe they are liable for.
Last winter the board was informed that bills to the construction firm had not been paid. After this discovery was made, several other financial situations were found.
The district has already used the funds it bonded for from district taxpayers for the building; therefore the district does not have dollars to pay off any outstanding balance.
Because the district is a public body, Gil Haugan must have a judgment against the district in order for the district to collect funds to pay off the bill.
How those funds get collected will not be determined until the legal process is complete.
Gil Haugan firm files suit for
unpaid bills
By
Lexi Moore, Editor, Hills Crescent