Geronimo Wind representatives told Rock County Commissioners Tuesday that May 1 is the targeted start date for pouring concrete pads for the 119 wind towers north and west of Luverne.
Pad construction will continue through June. Beginning in August, the towers will be set up at a rate of 10 per week.
At their meeting Tuesday, commissioners approved a conditional use permit for two more meteorological towers near the wind project in Sections 24 and 27 of Rose Dell Township.
County Attorney Don Klosterbuer said the additional towers were requested by the turbine manufacturers as part of guaranteeing their products.
Geronimo will remove the meteorological towers when they are no longer needed.
In other business the Board:
•Approved allowing the county engineer to push a federal grant request for a pedestrian underpass back one year or more.
•Approved a final payment of $38,332 to Central Specialties Inc. This $766,654.00 project was the reconditioning project on County State Aid Highway 17 from Beaver Creek to Trunk Highway 23.
•Approved $79,910 for the purchase of GPS survey equipment, 3D design software and three design computer workstations.
County Engineer Mark Sehr proposed using some of the $280,000 recapped in engine services on the Rock River bridge project.
Sehr said, “The three workstations will continue to allow us to do a lot of our own engineering work.”
Geronimo wind turbines go up May 1
By
Brenda Winter, Reporter