Letters were mailed to 40 homes in the neighborhood of the Bishop and Oakley intersection to alert them of a storm sewer project that will begin at the end of the month.
City Administrator John Call updated council members on the project during their Tuesday night meeting.
Several homes near the intersection have suffered damage two to three times this summer due to flash flooding, and engineers hope to relieve storm sewer pressure by installing a larger (46-inch) line in a two-block area.
Only a few homes actually suffered water damage but all 40 homes affected by the infrastructure improvement are being notified.
The homeowners were invited to a meeting Wednesday night to address questions about the project, such as how it will affect their trees, driveways, boulevards, garbage routes and more.
Henning Construction will be the contractor for the project at a cost of $92,500. Materials are estimated at $86,700. Costs will be covered by funds in the storm sewer account.
 
Assessing for unpaid bills
A portion of Tuesday night's Luverne City Council meeting was dedicated to a public hearing about assessments for unpaid utility and miscellaneous charges.
Various property owners owe the city more than $17,000, mostly in the form of unpaid utility bills.
According to city code, these unpaid bills can be assessed back to property owners on their next year's property taxes. A 4-percent interest rate is charged, but that can be waived if the bills are paid within 30 days of Tuesday's hearing.
No one attended the hearing to object to the bills, and no one submitted written correspondence, so Mayor Pat Baustian closed the hearing shortly after it was formally opened.
The council later took action to adopt an assessment for the unpaid bills.
City Administrator John Call said the council goes through this process every year to assess property owners for unpaid bills. This year, though, he said the unpaid amount is twice what it usually is.
According to state law, the city can't levy assessments for unpaid electric bills, but they can assess for unpaid water and sewer bills.
The assessments also include costs for mowing, snow removal, tree trimming and other improvements to private property that the city performed for property owners who neglected to do them.
 
In other business Tuesday, the council
•Adopted a resolution to set a public hearing for Nov. 5 to allow the council to issue bonds for capital improvements without an election being held.
Improvements under consideration are replacement of the roof and heating and cooling system at the city hall building, estimated to cost $400,000. The project is already in the five-year capital improvement plan.
•Adopted a resolution awarding bids for the electric distribution transformers related to the Gevo improvements.
Because of an expansion to the Gevo plant (formerly the Agri-Energy Ethanol Plant) the city's electrical distribution system needed to add a circuit to the west substation. This included underground wire and transformers.
The project is being completed using Missouri River Energy System personnel for the underground wire and the transformers have been competitively bid.
Border States Electric was awarded the bid at $213,846.