The Bureau of Reclamation recently notified Lewis & Clark Regional Water System officials that after indexing, the remaining federal cost share for the project has increased from $194.3 million last year to $200.6 million this year.
“This $6.3 million increase in the remaining federal cost share drives home the point that the federal funding being provided to Lewis & Clark is not even enough to keep up with inflation, let alone make any meaningful construction progress,” said Executive Director Troy Larson.
“Under this continued scenario, the project would never be completed.”
He said the trend points to continued delays in Lewis & Clark reaching Luverne and Rock County.
“In the federal government’s efforts to save money by gutting funding for Lewis & Clark, the taxpayers are being hit with a double-whammy,” Larson said.
“The longer it takes to complete the project the more expensive it becomes due to inflation and the longer it takes to realize the project’s many economic development benefits.”
By contrast, the three states and 20 local members have pre-paid $153.6 million, which equals 99.7 percent of the non-federal cost share.
Eleven members will begin receiving water later this summer when the treatment plant becomes operational, but the schedule to connect the remaining nine members is entirely dependent upon federal funding.
Project engineers estimate that if Lewis & Clark were to receive $10 million each year, the project would not be completed until 2050.
If the project were to receive $35 million a year, which is the amount requested annually, it is estimated the project would be completed in 2021.
“We greatly appreciate the hard work of congressional and administration officials through the years to bring Lewis & Clark to the verge of delivering water,” Larson said. “But we strongly urge these officials to re-double their efforts to ensure the project is completed in a timely and cost effective manner.”