County Highway Engineer Mark Sehr told County Board members Tuesday the July 14 deluge caused limited damage around the county.
“The water came up fast and went down fast,” he said about flooding, which caused temporary closing of County Road 4 west of Beaver Creek, County Road 5 west of Luverne and County Road 8 east of the state park quarry.
“We had a number of locations where gravel was washed off the roads,” he said, “but I don’t anticipate needing any emergency funding.”
Paving is scheduled to begin July 20 on County Highways 17 from Beaver Creek to State Highway 23 and on the approach to the recently finished bridge on County Road 8; weather permitting.
Sehr said so far this year, road repairs have amounted to “just patching. We’ve had some spring blowups to fix and we’re cutting back on bituminous because it’s expensive.”
Commissioners noted some roads are still experiencing potholes associated with the spring thaw.