What was described as a couple of finance "goofs" led to a decision by the Hills-Beaver Creek School Board to approve a request for Aid Anticipation Bonding.
Funding shifts in state payments have made it necessary for districts to seek short-term loans to pay monthly bills while they wait for their remaining funds to come in August or September.
This year the funding split gives school districts 60 percent of their funding throughout the year and the remaining 40 percent later.
Applying for Aid Anticipation Bonding was on the agenda at Monday night's meeting. The district has applied and used this funding option in the past.
Superintendent David Deragisch began the conversation by saying he had made "a couple of goofs" with the money collected from the $9.9 million construction bond.
These goofs play into the district being short funds to pay off the construction contractor.
Deragisch said, "When the smoke clears, we are about $100,000 short."
That figure includes approximately $205,000 coming from the city of Hills to cover the costs of bringing utilities to the property line and for a portion of North Summit Avenue.
The first goof Deragisch admitted to was in how he paid out the final construction bills.
He explained he was advised by other superintendents to withhold 5 to 10 percent of the final bills as a form of leverage to ensure work was completed.
Deragisch ignored calls coming in from Construction Manager Gil Haugan regarding the late bills.
Recently board chair Gary Esselink contacted the company and discovered that several of the subcontractors were not getting paid because of the district's failure to pay.
He was also informed that the district's contract with Gil Haugan was a bonded contract that required all subcontractors to be bonded as well. This protects the school from any negligence.
The second "goof" came in calculating when and how much money would be coming from the county via bond payments.
Deragisch took a $375,000 check to Gil Haugan last week and planned to deliver one for $200,000 this week, leaving $100,000 left to pay.
Esselink and Deragisch explained that the district would need to use funds acquired from a loan through the Aid Anticipation Bonding to pay the remaining amount.
This money needs to be paid back in the early fall.
Board members voted to approve participation and expect to see paperwork at their next meeting on Jan. 23.
At the conclusion of the meeting vice chairwoman Ann Boeve called for the building committee to meet to continue to discuss what to do with the various buildings owned by the district.
"We need to move forward with this,” she said. “It’s a possible revenue source, and we can't just sit on empty buildings.”

You must log in to continue reading. Log in or subscribe today.