County Board signs agreement with Geronimo to protect roads from construction wear

By
Brenda Winter, Reporter

Rock County Commissioners adopted an agreement with Geronimo Wind Energy to restore county and township roads after a wind tower project in northwest Rock County is completed in 2012.
Preliminary road work  in Rose Dell, Springwater, Mound and Denver townships begins this fall.
Geronimo attorney Christina Brusven and Rock County attorney Don Klosterbuer proposed a series of agreements regarding road maintenance and restoration so that “all expectations are known before heavy equipment starts out on the roadways.”
A firm will be hired to assess the condition of each road used during construction of the wind towers. Conditions like compaction, gravel depth and crown will be considered.
Geronimo assumes responsibility to restore the roads to their original condition.
According to Klosterbuer, “Some of the roads might end up in better shape than when they started. Geronimo will have a disincentive to tear up the roads, because they’ll have to fix them when they are done.”
Brusven said the agreement includes a two-year warranty after the roads are restored.
County Engineer Mark Sehr said part of the agreement includes Geronimo paying the county for Sehr’s time.
“This will be a yearlong project and will be taking a considerable amount of my time,” Sehr said, “maybe an hour or two every day.”
Geronimo will begin preparing some roads for heavy equipment this fall. 