Commissioners accept Judicial Ditch #2 report
Herreid Board Room 1:00 P.M.
Rock County Courthouse December 29, 2010
The Public Hearing was called to order by Vice-Chair Bakken with Commissioners Hoime and Jarchow present.
Kurt Deter, Attorney for the petitioners, informed the Board that they were prepared to accept the final contract for Ditch #2 with 3 conditions:
1. Engineer present a final As-Built report for the project.
2. That the order address the previously agreed to item of lowering the
inlet pipe.
3. That the appeal by the Land Owner be resolved upon receipt of the
As-Built report.
After the discussion motion by Hoime, seconded by Bakken to accept the report, carried on a voice vote.
At 1:12 p.m. the meeting was declared adjourned by the Chair Bakken.
(2-10)