Close proximity of those who signed up may allow rural water expansion to proceed

By
Brenda Winter, Reporter

Rock County Rural Water Manager Brent Hoffman updated county commissioners on the progress of a proposed expansion to the county’s rural water system at their Jan. 7 meeting.
Hoffman had some “good news, bad news” for the commissioners, saying that fewer people than expected had committed to being a part of a proposed expansion northwest of Luverne.
The good news, Hoffman said, is that most of the 22 who signed up live close together near the intersection of Springwater, Rose Dell and Mound townships.
Supporters of the project were hoping for at least 35 people to sign up, but the close proximity of those who did sign up may allow the expansion to go forward. 
If expansion proceeds, Hoffman said the project could end up saving quite a bit of money. 
In April, county commissioners authorized Rock County Rural Water to spend $19,000 for engineering and environmental studies as part of a possible expansion of the water system. 
The studies are required first steps in developing an expansion and funding plan. 
The proposal includes building a booster station and installing about five miles of 8-inch water transmission lines. 
Another part of the proposed project would include laying approximately 52 miles of new transmission and service pipelines along with a new water tower, possibly in Springwater Township. 
The estimated cost of the proposed expansion is about $4.3 million. 
 
The Rural Water fund has roughly $2.8 million in reserves, some of which would be used to pay for the expansion.