City to share cost of Hwy 75 roadwork

By
Lori Ehde, Editor

Luverne City Council members reviewed the upcoming South Highway 75 improvements at their meeting Tuesday night.
City Administrator John Call reported that Luverne officials had negotiated a deal with the Minnesota Department of Transportation to resurface Highway 75 as part of the city's improvements.
The work wasn't on the state's five-year plan, but because Luverne has agreed to shoulder 25 percent of the cost, state officials agreed to do it next year.
The total mill-off and overlay is expected to cost upwards of $2 million. That means the city's portion could come to $500,000.
"I'm hoping that's on the high end," Call said. "But I'd rather work with higher amounts and then be pleasantly surprised in the end if it's less."
The actual estimates are more like $1.7 for the total project, with Luverne's portion coming to $450,000, which includes engineering costs that the city also agreed to pay.
The money will come from the city's community development fund, which was established from the sale of the hospital.
The city has received $200,000 per year for five years, and a good share of that fund has been spent on airport improvements.
Now the remainder will be used on the Highway 75 mill-off and overlay.
"It was a case where we could do our share without increasing taxes and without using money from the general fund reserves," Call said.
A mill-off and overlay means the surface is ground off and a new layer of asphalt is applied.
In some areas affected by frost heaves, the pavement will be ground off to the subsurface and replaced with new materials.
The road surface work will be done all the way through town, from I-90 to the hospital with completion set for 2013.
 
Removing stoplights
and going to three lanes
Mayor Pat Baustian said the state will consider two changes as part of the Highway 75 project.
One is to remove the stoplight at Main Street and Highway 75 and replace it with stop signs.
"Street lights are expensive to maintain," Baustian reasoned.
The other is to change Highway 75 from four lanes to three, with the center lane reserved as a turn lane for left turns.
Baustian said public input will be considered for these items, as well as traffic counts.