The Hills-Beaver Creek high school building site is muddy but progress continues inside the building.
Superintendent David Deragisch gave Hills-Beaver Creek School Board members an update on the work during their meeting on Monday night.
He started by addressing issues with mud on the road leading to the site.
“We are keeping the trucks off the town roads,” Deragisch said. “It is a promise we made and we have to keep.”
He went on to say that he has talked to the construction manager about adding rock to the road to help with the mud, but they are concerned about contaminating the dirt.
If rock becomes mixed with the dirt, then it will not be usable in other places. Instead, they are dealing with the mud in a couple of different ways.
In the morning they are scraping down the main road and site, and they also plan to divert runoff alongside the road via trenches.
Deragisch said he is hoping for a dry spring and summer and is concerned that wet conditions would make it difficult to put in a road and parking lot.
“This is a big concern for us getting into the building when we want to. We don’t want to put in our road and parking lot on mushy ground.”
He continued, “I am glad we have this (current high school) building in case the conditions stay wet.”
Despite the muddy conditions, cement trucks are getting to the site and pouring floors throughout the building. In the main hallways, locker rooms and much of the north section of the building floors have been poured and are finished.
The stage area is ready but needs to be filled with three feet of gravel before it’s cemented.
Plans are to not pour the floor in the commons area until traffic stops. They will use this area to haul in gravel for the stage and supplies for other areas.
The gym floor will be poured all in one day.
Rough-ins for electrical and plumbing are completed in the classroom section of the building and are being worked on in the remaining areas.
The building committee met with a representative about seating in the gym.
A six-inch change in the specs led to the change in the size of the bleachers ordered.
Deragisch reported the new dimensions mean the district does not have to order custom-sized bleachers and stadium stairs. Instead they can get wider bleachers with more space by ordering a standard size.
Patriot Pride
•Deragisch recognized the school for its outstanding efforts in raising $2,300 for the Russell and Deb Kooistra family.
The high school collected money for two weeks as part of a coin war. The Kooistra family lost their house and belongings in a fire at the beginning of the month.
•The board recognized the players, coaches, fans and the band on their performance during the basketball playoff games.
They also discussed schedule changes for the playoff game at 5 p.m. on Thursday. Students will be released early to allow for buses to run their routes and return to the school in time for three buses to drive to Marshall for the game.
The buses will carry fans, players and band to the game.
The board also discussed plans if the team wins and qualifies for the state tournament.
•Noah Holthaus was selected to represent the district at the Minnesota Middle School All-State Band.
Band Director Dale Nelson submitted an audition tape for Holthaus, who plays trumpet in the middle school band.
He was selected from among 400 applicants to play in a band with 80 other musicians from around the state.
•A $250 donation was accepted from Wells Fargo Community Support. It will be used for supplies in the first-grade classroom.
Building site stays busy
despite muddy conditions
By
Lexi Moore, Editor, Hills Crescent