Building committee explores what to do with old buildings

Building Committee Chair Ann Boeve presented information on four pieces of district property during a Hills-Beaver Creek School Board meeting on Monday evening.
The four properties are the district’s current industrial arts building, the ag shop, the bus garage and the football field.
Boeve said the committee has been approached by people in the community regarding the future of these properties once school operations are moved to the new site.
During the past two weeks the group met with a local realtor to find out the potential of selling any or all of these properties.
The realtor offered numerous options, and Boeve said the group now wants get the properties appraised before moving forward.
They contacted two appraisers for quotes. The quotes ranged from $2,000 to $3,200 to do the work. One appraiser warned that it would be difficult to get an accurate value of the properties because there are no other comparable properties in Hills.
Boeve said the committee does not think it is worth spending the money to have the parcels appraised.
Other options would be to sell them at auction, accept bids or list the properties at a value the district decides.
She asked School Board members for direction on what they want the committee to do with the properties.
She said, “It is important for us to evaluate the district’s needs now and in the future.”
She pointed out that selling both the bus garage and ag shop is not an option unless it would bring in enough money to allow the district to build a new garage.
She added that the ag shop would have to be added to or retrofitted in order to store the current number of buses that use the bus garage.
She urged board members to talk to the community and one another to come up with options for these properties.
 
Start of school year
still unknown
H-BC Superintendent Dave Deragisch informed board members that the public is curious about whether or not the new high school building will be ready for the start of the upcoming school year.
He said his response is, “I don’t know.”
The construction team is trying to get the building completed for an August move-in, but work is being delayed because of issues with the road.
Boeve explained supplies are not being delivered because of access issues.
Deragisch said two to three weeks of sunshine can change a lot at the site.
Board chair Gary Esselink expressed concern for making sure the project is completed correctly instead of rushing to get it done by a specific date.
“This is more of an inconvenience than a problem; we want it done right.”
He continued, “We are a community of farmers, we understand the problems weather can cause. We need to deal with it and move on.”
Deragisch agreed. “We’d like to open in the new building,” he said, “but more importantly we don’t want them rushing to get the job done.”
He said the current building can house students if needed.
 
Construction update
Despite a delay with construction of the road, work continues inside the building.
•Bids are being collected for retrofitting the current high school gym locker rooms for heat. A boiler system was installed when the addition was built but was never used.
•Wood for the new gym floor is still on hold. Contractors are waiting on the road and geothermal work to start before delivering supplies for the flooring. The humidity of the room must be controlled before the wood can acclimate to the new environment.
•Flooring is being installed in the kitchen area.
•Wood doors for classrooms and offices are being installed.
•Installation of permanent lighting and the intercom system continues at the building.