Luverne ACE Hardware and the city of Luverne are teaming up to provide area residents safe disposal of fluorescent light bulbs.
Fluorescent bulbs and CFL bulbs contain hazardous materials that require special disposal.
In Rock County, residents currently take them to the transfer station east of Luverne and pay roughly $1 per bulb for their disposal.
Now ACE Hardware has agreed to serve as a collection point for the bulbs, and the city will pay to have them hauled away.
Instead of paying the full price for disposal, residents will pay 75 cents for each 5- to 8-foot fluorescent bulb and 50 cents for each shorter bulb.
ACE will keep that money as compensation for the service.
The city will pay for the containers and for the truck at $90 to $160 per load, depending on the load, to have them hauled to Green Lights Recycling, Blaine.
Robyn Wessels, city utility worker, presented the information to council members at their Tuesday night meeting.
She said the trucks will be called as needed, when the ACE containers are full.
City Administrator John Call commended the effort, calling it "the green thing to do. … I think it’s too tempting for people to put it in the trash stream.”
ACE Hardware has the containers at the store and is ready to accept bulbs.
Roof replacement at pool and fitness center
The City Council will take action at a future meeting to have the roof replaced at the pool and fitness center.
The 34-year-old roof is leaking and is due for a complete replacement.
Pool manager Samantha Honerman said water was running down the interior walls of the cardio room during the last hard rain.
Architectural Roofing Sheet Metal Inc. has provided a bid of $97,075 to replace 14,514 square feet of roof.
The company is the same one already hired to replace the roof over the City Hall and Minnesota West building this year.
Call said it’s a reputable company, and that the bid is fair. The city hall project is twice the size of the pool project and the bid is about the amount for similar materials. "I feel 100 percent good about this bid," he said.
He said about $60,000 has been set aside for pool depreciation and another $30,000 is in the pool budget. The council agreed to put the item on the next meeting agenda for formal action.
The intent would be for the pool roof to be replaced this summer or fall in conjunction with the City Hall roof project.
GEVO electrical upgrades
Rick Hoftiezer of Missouri River Energy Services informed council members Tuesday of the upgrades to the city's electrical distribution to meet demand by Gevo.
He showed photos of the 100,000-pound transformer being removed, improved and replaced at the city's west substation.
With the $450,000 improvements, the transformer nearly doubled its KVA rating. The addition of coolers and fans to the transformer were part of the upgrade.
He said the east substation and the west substation are nearly identical now, with the exception of a fifth circuit at the west substation dedicated to Gevo.
ACE accepting hazardous bulbs