The following appeared in the Rock County Herald on July 29, 1927:
FIRST MILE OF GRADING ON NEW NO. 9 ROUTE COMPLETED
Presence of sand slows up work, and contract may not be finished on schedule
Nearly a mile of grading on the new route for trunk highway No. 9 had been completed up to yesterday morning by the contractors.
That is, 4,900 lineal feet of highway from the South Dakota line, east on to the Bliss farm, had been finished. The work is not going anywhere near as fast as the contractors expected, however, for considerable gravel had been encountered and this is not handled as rapidly as dirt.
At the present time there appears to be some doubt as to whether the grading of the new highway will be fully completed before cold weather sets in, and when this work is finished surfacing of the road will remain to be done. This will provide for the distribution of about 1,600 yards of gravel to the mile, 1,200 yards of it being placed on the road and the remaining 400 yards in stock piles.
The task of graveling the road has not been considered by the highway department and it is understood that bids for the work will not be considered until it is definitely settled just when the grading will be finished.
Of the 6.7 miles of grading necessary for the rerouting of No. 6 at the south end, about two and one-half miles remain to be done. The contractor in charge of this work is moving about 5,000 cubic yards of dirt a week.
Donations to the Rock County Historical Society Endowment Fund can be sent to the Rock County Historical Society, P.O. Box 741, Luverne, MN 56156.
Mann welcomes correspondence sent to mannmade@iw.net.
1927 Herald: Gravel discovery slows county road work
Subhead
Bits by Betty
By
Betty Mann, Columnist