The following appeared in the Rock County Herald on December 10, 1926:
CONTRACTS FOR NEW HIGHWAYS AWARDED
Bids for Grading 6.9 Miles New Highway on No. 6, and 13 Miles on No. 9, Accepted by Babcock.
COST OF IMPROVEMENTS WILL EXCEED $138,351
Contracts Awarded will Carry Out Department’s Plan for Changing Trunk Highway Routes
The State Highway Department will spend $138,351 in Rock county next year on trunk highway improvements, plus whatever the department pays for right-of-way for the new highway between Luverne and the South Dakota state line.
This is according to announcement made the latter part of last week by C.M. Babcock, state highway commissioner, in connection with the letting of bids for trunk highway work.
Among the contracts awarded on bids received on November 30th, were two in Rock county — one for the grading of 6.9 miles on highway No. 6 between Luverne and the Iowa state line, and the other for grading of 13 miles between Luverne and the South Dakota state line.
The contract for the grading on No. 6 was awarded to C.W. McNamara, of Sioux Falls, at $23,496, and that for the culverts to Tobin & Maloney, of Madison, S.D. at $6,647.
The contract for the grading on No. 9 was awarded to Tobin & Maloney at $70,297; the culverts to the same firm at $29,384, and the 60-foot bridge at Beaver Creek to F. S. Bartlett, of Balaton, at $8,545.
These contracts do not include the gravelling of the new roadways, as the contracts for this work are to be let later.
As previously stated in these columns, the improvement on No. 6 is to straighten the highway from a point four miles south of Luverne so the road will extend straight south to the Iowa line, so that two railroad crossings can be eliminated, and the road shortened one mile, while the improvement on No. 9 embraces as entirely new route from Luverne to the South Dakota line. Under plans approved for the No. 9 improvement the road will parallel the Omaha railroad on the north side the entire distance from the west edge of the city of Luverne to the state line. This change will eliminate four grade crossings and shorten the route about three miles.
The matter of securing right-of-way for the No. 9 route has not yet been taken up by the department, but it is expected that this will be undertaken shortly.
In connection with the awarding of the above contracts, Commissioner Babcock announced that work on the projects will start as early in the spring as conditions will permit.
As the improvement of both routes is along lanes not now used as part of the trunk highway, the work will not interfere with traffic nor make any detours necessary, as the old roadways can be used during construction of the new roads.
Donations to the Rock County Historical Endowment Fund can be sent to the Rock County Historical Society, P.O. Box 741, Luverne, MN 56156.
Mann welcomes correspondence to mannmade@iw.net.
1926: Highway commissioner accepts project bids
Subhead
Bits by Betty
By
Betty Mann, Rock County Historical Society president